Legally present
  • Home
  • Article
  • Latest News Update
  • Law Schools
  • Supreme Court
  • Weekly Digest
Reading: Supreme Court: Arbitral Award Must Stay Within Contractual Parameters – SEPCO Electric’s Appeal Dismissed
Share
Legally present
  • Home
  • Latest News Update
  • Supreme Court
  • Article
  • know your lawyer
  • Weekly Digest
  • Home
  • Article
  • Latest News Update
  • Law Schools
  • Supreme Court
  • Weekly Digest
Follow US
Legally Present > Supreme Court > Supreme Court: Arbitral Award Must Stay Within Contractual Parameters – SEPCO Electric’s Appeal Dismissed
Supreme Court

Supreme Court: Arbitral Award Must Stay Within Contractual Parameters – SEPCO Electric’s Appeal Dismissed

Last updated: 2025/09/30 at 5:27 PM
Published September 30, 2025
Share

The Supreme Court of India recently delivered a landmark ruling in SEPCO Electric Power Construction Corporation v. GMR Kamalanga Energy Ltd. (2025 LiveLaw (SC) 963), reiterating that arbitral awards must strictly remain within the parameters of the agreement between parties. The Court dismissed the appeal of Chinese company SEPCO Electric, which had challenged the Orissa High Court Division Bench’s decision to set aside a nearly ₹995 crore arbitral award in its favour.

Contents
Background of the CaseIssues Before the Supreme CourtSupreme Court’s Reasoning1. Primacy of Contractual Terms2. Limits of Arbitral Power3. Scope of Section 37 Review4. Waiver and Equitable Estoppel Not PleadedKey Legal TakeawaysImpact of the JudgmentConclusion

This judgment is significant as it underscores the limited powers of arbitral tribunals, particularly in relation to Section 28(3) of the Arbitration and Conciliation Act, 1996. It reaffirms that arbitral tribunals cannot reinterpret or override express contractual terms under the guise of equitable doctrines such as waiver or estoppel.

Background of the Case

The dispute arose out of an EPC (Engineering, Procurement and Construction) agreement between SEPCO Electric Power Construction Corporation (SEPCO), a Chinese company, and GMR Kamalanga Energy Ltd. (GKEL).

In 2015, SEPCO abandoned the construction site, leading to disputes being referred to arbitration. In 2020, an arbitral tribunal awarded SEPCO nearly ₹995 crore, relying on a 2012 email exchange to hold that GMR had waived the contractual requirement of notice for raising claims.

However, the EPC agreement contained a clear “No Oral Modification” (NOM) clause, mandating that any waiver or variation must be agreed in writing and signed by both parties. The Orissa High Court Division Bench found that the arbitral tribunal had overstepped its authority by relying on an email to infer waiver, effectively rewriting the contract. The Division Bench therefore set aside the arbitral award under Section 37 of the Arbitration and Conciliation Act, 1996.

SEPCO appealed to the Supreme Court, arguing that the High Court had exceeded its limited scope under Section 37, which is narrower than Section 34 of the Act.

Issues Before the Supreme Court

The Supreme Court examined the following issues:

  1. Whether an arbitral tribunal can rely on conduct or email communication to infer waiver, despite the contract requiring a written waiver signed by both parties.
  2. Whether the High Court Division Bench was justified in setting aside the award under Section 37, given its limited scope.
  3. Whether Section 28(3) of the Arbitration Act mandates strict adherence to contractual terms, even where equitable considerations are invoked.

Supreme Court’s Reasoning

1. Primacy of Contractual Terms

The Court emphasised that arbitrators are creatures of the contract. Section 28(3) of the Arbitration and Conciliation Act explicitly requires arbitral tribunals to decide disputes “in accordance with the terms of the contract and taking into account the usages of the trade applicable to the transaction.”

The tribunal, by construing an informal email as waiver, departed from the express terms of the EPC agreement. The “No Oral Modification” clause barred any waiver or modification unless executed in writing and signed by both parties. Thus, the tribunal’s reliance on an email amounted to rewriting the bargain struck by the parties.

2. Limits of Arbitral Power

The judgment reiterated established precedents that arbitrators cannot go beyond the four corners of the contract. The Court observed:

“Numerous precedents laid down by this Court have often emphasised that an arbitrator lacks the power to deviate from or to reinterpret the terms of the contract while making an award. The awards must be within the parameters of the agreement entered between the parties.”

This ruling sends a strong message that arbitral awards based on creative reinterpretation of contracts will not survive judicial scrutiny.

3. Scope of Section 37 Review

SEPCO had argued that the Division Bench overstepped its powers under Section 37, since the scope of interference is narrower than under Section 34. The Supreme Court rejected this contention, clarifying that:

  • While courts must show restraint,
  • A “patent illegality” such as violation of Section 28(3) or ignoring an express contractual clause justifies intervention even under Section 37.

The Court held that both the arbitral tribunal and the Single Judge had erred in granting relief to SEPCO by assuming waiver, despite the EPC agreement mandating written consent. Thus, the Division Bench was correct in setting aside the award.

4. Waiver and Equitable Estoppel Not Pleaded

The Court also highlighted that SEPCO had never pleaded waiver or equitable estoppel in its case. By relying on an email to create a case of waiver, the tribunal introduced a new legal basis not advanced by SEPCO, which exceeded its jurisdiction.

This was a fundamental violation of arbitral procedure and contrary to Section 18 of the Arbitration Act, which ensures equal treatment of parties and adherence to pleaded claims.

Key Legal Takeaways

The judgment provides clarity on several important aspects of arbitration law:

  1. Arbitrators bound by contract: Section 28(3) mandates strict adherence to the terms of the contract. Arbitrators cannot introduce doctrines like waiver or estoppel to override express provisions.
  2. No Oral Modification Clauses enforceable: Where parties have agreed to a NOM clause, informal communications such as emails cannot substitute for written, signed agreements.
  3. Scope of judicial review: Even under Section 37, courts can set aside arbitral awards if they exhibit patent illegality or ignore explicit contractual stipulations.
  4. Doctrine of waiver must be pleaded: Arbitral tribunals cannot base awards on unpleaded legal doctrines. Doing so violates due process and the tribunal’s mandate.

Impact of the Judgment

This ruling will have a significant impact on arbitration in India, especially in infrastructure, EPC, and commercial contracts where NOM clauses are standard. It strengthens the principle that:

  • Contracts are sacrosanct.
  • Arbitrators cannot reframe agreements to suit perceived equities.
  • Judicial intervention, though minimal, remains available where awards contravene express contractual provisions.

For foreign investors and companies engaging in arbitration in India, this decision provides certainty and predictability. It reassures parties that tribunals cannot bypass contractual safeguards, and courts will intervene in cases of blatant deviation.

Conclusion

The Supreme Court’s decision in SEPCO Electric Power Construction Corporation v. GMR Kamalanga Energy Ltd. is a reaffirmation of the sanctity of contracts in arbitration law. By dismissing SEPCO’s appeal, the Court made it clear that arbitral tribunals cannot reinterpret contractual terms or create new doctrines not contemplated by the parties.

The ruling will be cited as a precedent to ensure that arbitration remains a contract-governed process, not an exercise in equitable discretion. With this judgment, the Supreme Court has once again drawn a fine balance between respecting arbitral autonomy and upholding the binding force of commercial agreements.

Also Read

Delhi High Court Restrains Rupa Publications from Selling Constitution Edition Resembling EBC’s Red-and-Black Coat Pocket Edition

Supreme Court Calls for Performance Evaluation of High Court Judges: A Step Towards Judicial Accountability

You Might Also Like

Improper For HC Judge To Not Refer Bail Plea To Earlier Judge Citing Roster Change: Supreme Court

Motor Accident Compensation: Supreme Court Clarifies Minimum Wage Assessment in Sharad Singh v. HD Narang

Supreme Court Reprimands Magistrate for “Abdicating Jurisdiction” After Missing Deadline

Supreme Court Rules: Trial Court Cannot Take Cognizance of Offence Not in Chargesheet Solely on Private Witness Affidavits

Supreme Court Dismisses Karnataka’s Plea Against DM Gaming: Poker’s Status as Game of Skill or Chance Left Open

TAGGED: Arbitral Awards, SEPCO, Supreme Court
Share This Article
Facebook Twitter Whatsapp Whatsapp LinkedIn Telegram
Leave a comment

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Weekly Newsletter

Subscribe to our newsletter to get our newest articles instantly!

[mc4wp_form]
Popular News
Arrest right
Article

What are my rights if I get detained by the police?

Vanita Vanita April 10, 2025
Supreme Court to Hear Tamil Nadu’s Suit Against Karnataka Over Pennaiyar River Dispute on September 23
Supreme Court Raps AIADMK MP CV Shanmugam in “Ungaludan Stalin” Scheme Case; Imposes ₹10 Lakh Costs
Kerala High Court: Trial Judges Must Personally Verify Obscene Videos Before Conviction
Supreme Court Seeks Compliance Affidavits From States and UTs on POSH Act Enforcement: All You Need to Know
lawferAd image
lexibalAd image

Categories

  • Supreme Court
  • Latest News Update
  • High Court
  • Article
  • know your lawyer

About US

Legally Present is an Indian legal news platform covering court judgments, legal rights, and insights for law professionals and students.
Quick Link
  • My Bookmark
  • InterestsNew
Top Categories
  • Advertise with us
  • Newsletters
  • Deal

Subscribe US

Subscribe to our newsletter to get our newest articles instantly!

[mc4wp_form]

© Legally Present All Rights Reserved.